Energy Resources

RENEWABLE HYDRO POWER FOR THE NORTHWEST

The Clear Choice

ARROWROCK

The PUD, along with five irrigation districts from Idaho and Oregon, have developed this 18 megawatt hydroelectric project and power production started in early 2010.  The project was added to an existing dam and no new impoundments were required.  Existing water releases will generate the electricity through the two- 9 megawatt turbines.  The project will benefit large numbers of Idaho farmers and water users by helping offset the operating costs of their increasingly expensive water delivery system.  No negative environmental impact was found as a result of this retrofit to the Arrowrock Dam.  Clatskanie PUD committed to this project as a way to acquire new, clean renewable resources to meet future electrical load growth, particularly for local business and industry.  Clatskanie PUD will be purchasing all of the power generation from the project.

Read the feature cover story on the project in the NWPPA Bulletin Magazine
Ribbon Cutting Ceremony video March 23, 2010, Courtesy of the Idaho Statesman

Jan. 26, 2010 – Video of Testing of Unit #1
Video 1
Video 2

Jan. 28, 2010 – Video of Unit #1 synchronized with Idaho Power System and load rejection test successful
Video 3

Past Press Releases on the project:
March 30, 2010
March 15, 2010
September 2, 2009
July 21, 2009
February 23, 2009
November 6, 2008
October 16, 2008
August 11, 2008

ARROWROCK PHOTO GALLERY

May – July 2009
July 21, 2009
Aug – Dec 2009
Dec. 2009
March 2010
March 2010
Clatskanie attendees at dedication
Greg Booth speaking at dedication
Dedication 3/23/10
Dedication 3/23/10
Dedication 3/23/10
Dedication 3/23/10

October 2008 – April 2009 Photos

CO-GENERATION PROJECT

Clatskanie People’s Utility District (PUD) and the Eugene Water and Electric Board (EWEB) constructed a 36-megawatt (MW) cogeneration facility at the Georgia Pacific Wauna Paper Mill located along the Columbia River near Clatskanie, Oregon, approximately 75 miles northwest of Portland. The project was completed and began generating power for use in the region in mid-1996.

The cogeneration facility generates electricity directly from process steam currently produced at the Wauna Mill before that steam is used in the papermaking process. The cogeneration facility, including a generator and turbine, is constructed on property leased from Georgia Pacific.

To increase the available amount of steam, a fluidized bed boiler has also been constructed. This boiler burns “sludge” – a moist sawdust-like, non-hazardous waste product of the papermaking process – from the mill, which is, currently land filled on site. Natural gas may also be used to occasionally co-fire the boilers.

The output is to be sold to the Bonneville Power Administration. Under the terms of the Power Purchase Agreement for the project, Bonneville will purchase the project output over a 20 year period at a fixed rate on a “take and pay” or output basis. Prior to agreeing to purchase the output, Bonneville completed an Environmental Assessment for the project with a Finding of No Significant Impact. This 20 year agreement ends April of 2016, and the power will then be split between EWEB and Clatskanie PUD as well as the costs for the power.

The project is directly connected to the Bonneville electric transmission system at the Wauna Mill. As a result, there was no need to build transmission facilities for the project nor is there any cost of transmission.

Georgia Pacific, the PUD and EWEB have executed a variety of construction, operation and maintenance agreements for the project. Under the terms of those agreements, Georgia Pacific served as the project construction manager for the two utilities, and now that the generator is in service, Georgia Pacific will also operate and maintain the facility. The various agreements also include definition of roles and responsibilities for such things as; sale of steam from the existing boilers, delivery of sludge to the fluidized bed boiler, and the site lease.

 

WGA Financial Statements: